Lagos Reopens Ogudu-Ifako Bridge After Completing Repairs in 73 Days
The Lagos State Government has officially reopened the Ogudu-Ifako Bridge after completing repair works on 400 metres of its four expansion joints, restoring smooth traffic flow along one of the busiest routes in the state.
The bridge, inbound Alapere, was closed to traffic on June 28 for scheduled repairs expected to last 100 days. However, the project was completed in just 73 days, earning praise from residents and government officials alike.
Faster Completion Than Scheduled
According to the Special Adviser on Infrastructure, Olufemi Daramola, the repairs were initially projected to take 101 days but were finished early due to the dedication of contractors, cooperation from security agencies, and patience from Lagosians.
He explained that the expansion joints, if left unattended, could have compromised motorists’ safety and further weakened the structure.
“We undertook this repair to guarantee safety. Thankfully, with the cooperation of the people, we have been able to deliver ahead of schedule,” Daramola said.
Government Officials Inspect and Certify the Works
Daramola, alongside the Commissioner for Transportation, Seun Osiyemi, inspected and certified the project. Osiyemi thanked Lagos residents for their patience, promising that the state will continue its infrastructure renewal drive.
“This success belongs to everyone. Lagosians endured the inconveniences and supported the process. We sincerely appreciate your perseverance and patience,” Osiyemi stated.
He also urged residents to protect the bridge and other facilities, reminding them that these projects are funded with taxpayers’ money.
Next Stop: Maza-Maza Maintenance
The government disclosed that similar maintenance works will soon begin in the Maza-Maza area as part of the ongoing bridge rehabilitation programme. Previous projects at Odo-Iyalaro and Apongbon bridges have already been completed, with several others underway.
Residents Welcome the Reopening
Commuters expressed relief at the reopening. Ms. Adebisi Adesesan said the repair will reduce traffic gridlock:
“We suffered long hours during the closure, but this is worth it.”
Commercial driver Mr. Taofeek Shittu added that the reopening will reduce fuel costs and travel time:
“Traffic was terrible. This reopening is a big relief for us.”
Bridge Now Fully Open to Traffic
The officials officially declared the Ogudu-Ifako Bridge open, restoring unrestricted vehicular movement and easing congestion for thousands of daily commuters.
With the project delivered ahead of schedule, the Lagos State Government says it remains committed to providing safe, durable, and sustainable infrastructure for a greater Lagos.